Brickwork of the walls of section A-1 is underway
RIEL Real Estate Corporation continues to inform about the active construction of the Hyde Park Club House.
At the moment, the following works are being carried out at the facility: in section A-1.1, the brickwork of the walls of the fifth and sixth floors continues, the arrangement of ventilation units for residential premises is underway, and the laying of ventilation ducts for commercial premises has been completed. Work is also underway to install sewer and water supply risers. At the same time, the workers started arranging flat and hipped roofs.
In section A-1.2, work is underway to erect a monolithic frame at the level of the first residential floor. At the same time, the retaining wall of section A-2 is completed.