Installation of ventilation ducts and chimneys in section A-1 is in progress
November 19, 2024
RIEL Real Estate Corporation continues to inform about the active construction of the Hyde Park Club House.
The following works are currently underway at the facility:
- - installation of ventilation ducts and chimneys in section A-1.1;
- - brickwork of the fifth floor walls is in progress;
- - foundation of section A-1.2 has been completed, and the installation of vertical parking lot columns has begun;
- - construction of the supporting wall of section A-2 is nearing completion.